H2O Xtream December Update

Published on 13 December 2024

H2O December update-14 website photo.jpg
One more H2O Xtream Aquatic Centre update before the end of the year.

  • The Jr Leisure Pool, tiles and pool linings are under way in the pool.
  • The changing rooms are getting their doors installed and the flooring and showers are well underway.
  • The installation of the slides is complete and cladding of the tower is ongoing. (Learn more about these on our project page).
  • The ventilation above the pool is installed, tiling and resealing of the pool is complete!
  • The installation of the services is ongoing.
  • The flooring, joinery and ceilings are all installed.
We're still on track for opening early next year and you can find out more by visiting the project page by clicking here.

 