Pinehaven Stream Improvements

Pinehave Streamworks.jpeg

Wellington Water, on behalf of Greater Wellington Regional Council and Upper Hutt City Council, has been leading work to upgrade and increase the capacity of the Pinehaven Stream to reduce flood risk for the surrounding community.

Following the completion of works in the Willow Park area, project delivery responsibility has now transitioned back to Upper Hutt City Council and Greater Wellington Regional Council.

The review recommended exploring alternative design and delivery options for future stages of the Pinehaven Floodplain Management Plan over the next 12 months. While this may cause some delays, the overall objective—to reduce flood risk and enhance community resilience—remains unchanged and aligned with the approved plan.

We will continue to keep the community informed as the project progresses.

August 2025

Future of Pinehaven Stream Upgrades Under Review Following Key Project Milestones  

Upper Hutt City Council and Greater Wellington Regional Council are now reviewing the next phases of Pinehaven Stream flood protection after resuming management of the project following completion of phase 1 and 2 by Wellington Water Limited..  

The Pinehaven Stream upgrade is a long-term initiative to improve stormwater resilience and reduce flood risk in the Pinehaven area.  

With construction works in Willow Park completed, the councils undertook a comprehensive review of the project and its objectives. This review was discussed at the Te Awa Kairangi / Hutt River Valley Subcommittee meeting on 13 May.  

As part of the review process, officers assessed the remaining three stages of the project, which primarily involve work on private property, including access bridges and concrete channels.  

The review identified a substantial increase in overall project costs—from the original estimate of $10.9 million to a current projection of $58.6 million.  

With $22.5 million already spent, the cost to complete the remaining stages is now estimated at $36.1 million.  

Given the rising costs and complexity, the review recommended a pause in construction while alternative design and delivery options are explored over the next 12 months.  

Upper Hutt City Council’s Group Manager Operations, Tim Harty, says these options may include a more naturalised stream channel with fewer built structures, or an approach focused on maintenance and emergency response rather than major infrastructure works.  

 

We are in the process of working with the most directly affected properties

 

Phase 1: May 2021 – June 2022. Complete

Work to upgrade two culverts within the Pinehaven Stream that form the road crossings on Sunbrae Drive and Pinehaven Road was completed in early 2022. The Phase 1 works included:

  • Replacing the existing culverts with larger culverts and headwalls that meet current seismic and roading standards
  • A new roundabout at the Pinehaven Road/Blue Mountains Road intersection
  • New footpaths, fencing and planting.
  • The removal of 48 Blue Mountains Road and 4 Sunbrae Drive. This property was identified as  flood prone during investigations into flood protection and GWRC acquired it as part of that project.
  • After the removal of the house the land was levelled and grassed as a temporary measure before the Phase 2 works start.

Read more here

 

 

Phase 2: September 2023 – Mid-2024. Completed

Phase 2 stream improvements, funded for $5 million, will begin in 2023 in the Willow Park area immediately downstream of the Phase 1 works and will include:

  • Widening the section of stream through Willow Park from Sunbrae Drive to Blue Mountains Road.
  • Building new retaining walls immediately downstream of the Sunbrae culvert.
  • Widening the stream banks (without retaining walls) further downstream, where there is more space available.
  • Removing the existing pedestrian bridge over Pinehaven Stream at Willow Park and replacing it with a new pedestrian and cycle bridge linking to 4 Sunbrae Drive.
  • Improving the pedestrian path through Willow Park.
  • New and replacement planting of native trees and plants.
  • Upgrading the junction where Pinehaven Stream joins Hulls Creek (by the Silverstream Railway Station) to make it easier for fish and eels to travel between the two watercourses

 

 

FAQ's

What is the Pinehaven Stream Upgrade Project?

The Pinehaven Stream Upgrade is a long-term project aimed at reducing flood risk and improving stormwater resilience in the Pinehaven area.

 

Why is the project under review now?

After completing the Willow Park section of the works, Upper Hutt City Council and Greater Wellington Regional Council took back project management responsibilities from Wellington Water. They are now reviewing the next phases of the project to assess whether the original design is still the most effective and cost-efficient option moving forward. 

 

What did the review find?

The review found that the cost to complete the remaining stages has increased significantly—from an original estimate of $10.9 million to around $58.6 million. About $22.5 million has already been spent, and completing the rest would cost approximately $36.1 million. 

 

What parts of the project are still to be completed?

The remaining work is being reviewed, with the current proposal primarily focusing on activities on private properties, including the replacement and removal of access bridges and concrete channel upgrades. 

 

What is happening now that the review is complete?

Potential alternatives include: 

  • Current design option – complete the design that was originally agreed to. This   design includes significate work in the existing channel with the use of large concrete structures to keep the stream within the channel in the event of flood events.  This will require a number of new stream crossings to allow for property access. 
  • Naturalisation of the channel – remove many of the existing structures and bridges that currently constrain the flow in storm events and widen the channel to increase the capacity of the stream.  This would involve significant earthworks and planting.  It may also include the targeted purchase of property to facilitate the work.
  • Maintenance and clearance – undertake vegetation clearance and channel clearing to improve the flow of flood water in the existing channel.  This option would involve less initial work, but ongoing work to maintain the stream 

 

What alternative options are being considered?

  • Current design option – complete the design that was originally agreed to. This   design includes significant work in the existing channel with the use of large concrete structures to keep the stream within the channel in the event of flood events.  This will require a number of new stream crossings to allow for property access. 
  • Naturalisation of the channel – remove many of the existing structures and bridges that currently constrain the flow in storm events and widen the channel to increase the capacity of the stream.  This would involve significant earthworks and planting.  It may also include the targeted purchase of property to facilitate the work.
  • Maintenance and clearance – undertake vegetation clearance and channel clearing to improve the flow of flood water in the existing channel.  This option would involve less initial work, but ongoing work to maintain the stream 

 

Will the public be able to consult on the options provided above?

Wider public consultation will be undertaken in early 2026 once the feasibility of the options has been determined.  

 

Who is overseeing this next phase of planning?

A Pinehaven Steering Group has been re-established, made up of representatives from: 

  • Upper Hutt City Council 
  • Greater Wellington Regional Council 
  • An independent project manager 

This group will meet monthly to evaluate and guide future options. Its work is overseen by the Te Awa Kairangi/Hutt River Valley Subcommittee. 

 

How will the community be kept informed?

Updates will be posted on the Upper Hutt City Council’s Pinehaven Stream Improvements webpage. A dedicated email address (pfm@uhcc.govt.nz) is also available for community questions. 

 

What if my property is still at risk of flooding?

We understand this pause may be frustrating for residents still at risk. The current focus is on finding a solution that effectively manages flood risk while ensuring long-term value for the community. 

 

When will a decision on the next steps be made?

A preferred approach is expected to be identified within the next 12 months after thorough assessment of all alternative options. 

 

 

 